UAT template for software project handover: how to sign off with confidence
User acceptance testing (UAT) is the stage where your own team tests a software project against its real working scenarios before signing the handover. The template below is ready to copy and has four parts: the test plan (who tests, on which environment, with what data), test scenarios written step by step with the expected result, an issue log with severity levels, and an acceptance record with clear criteria. It works for signing off a website, an app or an internal system such as an ERP or CRM. The key rule: write scenarios from the document the project was priced on, so the judgement is about what was agreed, not new ideas. Send Fortune Code your project scope and we reply with a written quote within 24 hours.
On this page
When and how to use the UAT template
Acceptance testing comes after the agency has finished its own testing, and before go-live and the handover payment. It is done by the staff who will use the system every day, not by the developers.
Copy the parts below into a shared sheet and agree the template with the agency before testing starts: who writes the scenarios, how long a test round lasts, how long fixes take, and when the project counts as accepted.
Part 1: The test plan
One page that prevents the most common handover disputes: “we never tested that” and “that is out of scope”.
- Project name and release: [name, version]
- Reference document: [name and date of the approved requirements or proposal]
- Test environment: [link to the test version, not the live one]
- Testers and roles: [name, department, system role: manager, staff, customer]
- Devices and browsers: [iPhone, Android, desktop, the browsers your team uses]
- Test data: [sample customers, items and orders that resemble real ones]
- Test round duration: [working days]
- Fix and retest period: [working days]
- Final sign-off by: [name and title]
Part 2: Test scenarios
Each scenario is a real operation from the working day, end to end. Write it with these fields and repeat for every operation in scope:
- Scenario ID: [UAT-01]
- Function: [e.g. create a quotation and convert it to an invoice]
- User: [the role that runs the scenario]
- Precondition: [e.g. a registered customer and an item with a price]
- Steps: [1. ... 2. ... 3. ...]
- Expected result: [exactly what should appear, be saved or be sent]
- Actual result: [what happened]
- Status: [pass / fail / pass with note]
- Tester and date: [name, date]
Scenarios people often forget to test
The happy path always gets tested. Costly bugs hide in the cases nobody tries. Add these to your list:
- Permissions: a user with limited rights tries to open a screen or report they should not see.
- Cancel, edit and refund, not just create.
- Bad input: an empty field, a short mobile number, a negative quantity, a past date.
- Arabic: long names, Arabic search terms, printing and exporting to PDF and Excel.
- Hijri dates if required, and time zones if you have branches outside the Kingdom.
- Invoices: VAT, rounding and the VAT number, and e-invoicing compliance if it is in scope.
- Notifications: does the WhatsApp message, email or SMS reach the right person with the right text.
- Performance: opening a full-year report, or a list with thousands of records.
- Migrated data: a sample of customers and old balances matches the previous system.
Part 3: Issue log and severity levels
Log every issue on one row with the fields below. Severity decides what blocks acceptance and what is fixed after it.
- Issue ID: [BUG-01]
- Linked scenario: [UAT-01]
- Description: [what happened, and what was expected]
- Steps to reproduce: [1. ... 2. ...]
- Screenshot or recording: [attached]
- Severity: [critical: stops work or corrupts data / high: core function broken with a workaround / medium / low: cosmetic]
- Type: [bug / change request outside scope]
- Status: [open / in progress / fixed / retested and closed]
Part 4: The acceptance record
The record is signed when the agreed acceptance criteria are met, not when every cosmetic note is closed.
- Project and release accepted: [name, version, date]
- Scenarios run: [number], passed: [number]
- Acceptance criterion: [no open critical or high issues]
- Open medium and low issues: [list, and fix date]
- Change requests outside scope: [list, priced separately]
- Deliverables: [source code, login details for all accounts, user guide, team training]
- Post-launch support starts: [date]
- Signatures: [client representative] and [agency representative]
Common handover mistakes, and how we work
The usual ones: testing on the live system with real customer data, mixing new change requests with bugs, only the manager testing instead of the staff, and signing acceptance before the code and accounts are handed over.
At Fortune Code we build the acceptance plan with the client from the scope document itself, payments are staged and tied to deliveries, and the code and accounts are handed over in your name, with delivery on the written date and fast technical support after launch. Send us your project scope and we reply with a written quote within 24 hours.
Our commitments
You own the code
Source code, accounts and domain are in your organisation’s name from day one.
Written scope and contract
Scope, milestones and price are agreed in writing before the first line of code.
On-time delivery, guaranteed
The delivery date is written into the contract, and we keep it at every milestone.
Fast technical support
A team that responds quickly after launch and fixes any issue in production.
How we work with you
- 1
Free discovery session
30 minutes with an engineer to understand your needs and how you work.
- 2
Written proposal within 24 hours
Clear scope, milestones, timeline and a price in SAR, with no obligation.
- 3
Contract and staged payments
You pay in stages tied to deliveries, not everything upfront.
- 4
Delivery with weekly reports
Follow progress in the client portal and review every milestone before sign-off.
- 5
Launch, training and support
We launch on schedule, train your team and stay with you with fast support.
Request a quote
Tell us what you need for “Maintenance & Technical Support” and a specialist will send a written proposal with scope, timeline and price within 24 hours.
Frequently asked questions
What is user acceptance testing (UAT)?
Testing carried out by the client’s own users on a software project before handover, using their real working scenarios, to confirm that what was delivered matches what was agreed. It comes after the agency’s testing and before go-live.
Who writes the test scenarios?
Ideally the client, with help from the agency, because the client knows its daily operations. What matters is that they are based on the approved requirements and agreed before testing starts.
Should I refuse handover over cosmetic issues?
Usually not. The common criterion is that a project is accepted when no critical or high issues are open, with minor issues listed in the acceptance record and a date to fix them.
What is the difference between a bug and a change request?
A bug is something in the agreed scope that does not work as described. A change request is something new or different from what was described. The first is fixed within the project; the second is priced and scheduled separately so handover is not delayed.
How long does acceptance testing take?
It depends on project size. A company website may need two or three days, while an internal multi-department system may need two rounds or more. What matters is that the duration is written in the test plan in advance.
What should I receive with the acceptance record?
The source code, login details for every account (hosting, domain, app stores, connected services) in your organisation’s name, the user guide, team training, and the start date of post-launch support.
Guides and prices to help you decide
- How Much Does It Cost to Build a Mobile App in Saudi Arabia in 2026?
- How Much Does an ERP System Cost in Saudi Arabia in 2026?
- How Much Does an Online Store Cost in Saudi Arabia in 2026?
- How Much Does an Appointment Booking System Cost in Saudi Arabia in 2026?
- How to choose a mobile app development company in Saudi Arabia: questions, red flags and what a good proposal contains
- How to choose an ERP system for a small or mid-sized company: from need to go-live
- A website, a mobile app, or both: what your business needs and in which order
You may also need
Ready to start?
Send us your idea on WhatsApp and get a written proposal with scope, timeline and price within 24 hours.
Talk to us on WhatsAppLast updated: